The solar kit

What a solar PV label kit contains

Start with the plate list for your system, then set the quantities for your job. The catalogue examples below include 20 base label types for a string-inverter system and 16 for microinverters. Repeated plates, storage, province and utility details can change your final list and piece count.

Already have a drawing or plate schedule? Send your plate list for a quote →

The claim to be careful with

Kits advertised as “four plates per install” are built to the American NEC — 690.31(D) and 690.56(C). Those rules don’t govern in Canada. An inspector working from C22.1:24 Section 64 and your utility’s interconnection standard is looking for a different set, different wording, and in British Columbia a different colour entirely.

Five questions decide the kit

Not the system size. Two 9 kW rooftops one street apart get identical kits. The same rooftop moved from Burlington to Saskatoon gets a different kit and different wording.

01 — Where
Province, then the LDC

The province sets the base rule set. The local distribution company adds its own plates on top.

02 — Interconnection
Grid-tied?

Grid-tied pulls in the whole interconnection block. Off-grid drops all of it and adds the stand-alone power system notice — roughly half the area.

03 — Inverter
Accessible DC circuit?

The biggest swing in the kit. String or central means a DC ratings plate and ungrounded warnings; micro or AC modules takes them out. 20 plates vs 16.

04 — Storage
Battery or ESS?

Storage adds a self-contained 8–11 label block. Multi-part ESS in Ontario adds the UL 9540 evaluation label.

05 — Occupancy
Dwelling or not?

CEC 2-306 arc-flash marking applies “other than dwelling units.” A house never gets one; a commercial rooftop always does.

The rest
Is just counting

Inverter count, points of interconnection, combiners, disconnecting means, transformers, generators with transfer switches.

The four plate sizes

Universal vendor sizes used across the catalogue
SizeMetricUsed forWhat it carries
11″ × 8.5″279.4 × 215.9 mmDiagram platesThe single-line diagram, the site plan and the rapid-shutdown location plates — the tags that carry a drawing.
5″ × 2″127 × 50.8 mmMain warningsMain service warnings, including the dual-power-supply plate at the meter and utility disconnect.
8″ × 2″203.2 × 50.8 mmLong warningsWarnings whose wording runs long, like the energy-storage warning at the service where a battery is on site.
4″ × 1″101.6 × 25.4 mmEquipment IDOne-line equipment identification. Up to four plates per province use it.

Worked kits

Ontario kits, straight out of the kit generator
JobPlates
House — string inverter20
House — microinverters16
House — with battery24
Commercial rooftop29
Ground mount / solar farm31
Off-grid / cabin15
Re-label an existing install7

The twenty, one by one

A grid-tied house on a string inverter, no storage, base set before the province and the utility add theirs. 5 of these carry blanks that come off your drawings — voltages, currents, locations — and are engraved with the values rather than shipped for someone to write on.

House — string inverter, 20 plates
PlateRuleType Where it goes
Single-line diagram of the interconnected system84-030(2) · 64-218(6) · 64-104(5)IdentificationConspicuous location at the supply authority disconnecting means; NSP also requires it inside at the main service panel and any PV sub-panels.
Interconnected system warning notice84-030(1)WARNINGAt the utility disconnect and the meter location.
Photovoltaic power source placard84-030(1) once reworded to MB24 items 8-9 text; house as currently engravedCAUTIONAt the meter base / service equipment as directed by the utility.
Rapid shutdown placard at meter and service equipment64-218(7)IdentificationAt the supply authority meter location and the consumer's service equipment location. On buildings without exterior metering the location may need to be agreed with the local fire department.
AC disconnect - shock hazard, two sources64-060(1)(h) · 84-024(1)(i)WARNINGAll AC disconnects supplied from two sources of power, and every energy storage system disconnecting means (CEC 2024 Rule 64-914).
Photovoltaic AC disconnect marking64-074(1)IdentificationEach interconnecting AC power source - AC disconnects for inverters, panelboards, splitters.
AC raceway / conduit markerhouseIdentificationOn raceways and enclosures carrying the PV AC output circuit.
Photovoltaic DC disconnect marking64-200(1)IdentificationString inverters - PV output circuit DC disconnect, at an accessible location.
Rapid shutdown at the DC disconnect64-200(2)IdentificationAt the disconnecting means for the photovoltaic output circuit.
DC raceway / conduit markerhouseWARNINGOn raceways, cable trays, enclosures and junction boxes carrying PV DC circuits, at intervals set by the AHJ.
DC conductor polarity - positive64-212(3)-(4) · 64-908(a)(ii) (ESS dc)IdentificationOn multi-conductor PV cable (e.g. TECK 90) where colour coding is field-applied under 64-212(3), at every point where conductors are exposed. Not for single-conductor RPV/RPVU, which 64-212(2) bars from field marking.
DC conductor polarity - negative64-212(3)-(4) · 64-908(a)(ii) (ESS dc)IdentificationOn multi-conductor PV cable (e.g. TECK 90) where colour coding is field-applied under 64-212(3), at every point where conductors are exposed. Not for single-conductor RPV/RPVU, which 64-212(2) bars from field marking.
DC arc-fault protectionhouse (64-216 requires annunciation, not a label)IdentificationAt the inverter or combiner providing DC arc-fault protection.
Backfed breaker - do not relocate64-112(4)(c)WARNINGAt the PV input breaker in the electrical panelboard.
Multiple power supplies14-414(3) · 64-112(4)(d)WARNINGInverters and equipment fed from two sources - one per source disconnect, or one label indicating multiple disconnects must be opened.
Do not upsize main breakerhouseWARNINGAt the main breaker of a panelboard with a PV interconnection.
Inverter identification2-100IdentificationOn or adjacent to the inverter.
Array boundary / roof markinghouseWARNINGAt the array boundary and roof access points.
Firefighter / first-responder placardhouseNOTICEAt the main entrance or service entrance, per the fire authority.
Emergency shutdown procedurehouseNOTICEAt the main service disconnect and the inverter.

Rule numbers are printed as the source document writes them, and most provincial and utility standards were drafted against the 2021 Code. Nine Section 64 numbers changed in C22.1:24 — the renumbering is here.

Microinverters remove the DC block and take it to 16. Storage adds a self-contained block and takes it to 24. The warning plates in detail · the placards · print the checklist.