Manitoba solar label kits
Manitoba Hydro is one of two utilities in Canada that require engraved plates by name; Nova Scotia Power is the other. Informative Bulletin 64-0 states that solar photovoltaic labels are to be engraved lamacoids, red background with white lettering. Everywhere else it is an accepted example. Here it is the requirement.
277 square inches of engraved. Microinverters are 17 plates.
The wording is the utility's own.
Red background, white lettering, engraved. IB 64-0 says so outright.
A utility that names the product
Why it matters
Across most of Canada a printed vinyl label can satisfy an inspector, because the Code asks for permanence and legibility rather than a process. Manitoba Hydro, like Nova Scotia Power, removed the choice. In its territory a printed label is simply the wrong product.
That one sentence in Informative Bulletin 64-0 is the reason a Manitoba job is the easiest one on this site to specify: there is nothing to argue about.
The site plan
Manitoba is also unusual in what it asks the plates to show. Two of the 14 are locators rather than warnings: a meter location and service box diagram, and a callout that tells a responder where the utility disconnect actually is. Those carry job-specific content, so they cannot be stocked and cannot be guessed. Send the site plan with the order.
That an engraved lamacoid from us carries an approval of its own, or that it will pass an inspection by itself. Manitoba Hydro's bulletin describes a product, and we make that product to its description. Approval attaches to the installation as inspected, never to a plate in a bag.
The locator plates and the disconnect identifiers carry blanks for voltages, currents and locations. The builder asks for those values and engraves them. An inspector is entitled to refuse a Sharpie.
The 14 plates Manitoba Hydro words for you
| Plate & rule | Where it goes |
|---|---|
| Multiple power supplies 14-414(3) · 64-112(4)(d) | Inverters and equipment fed from two sources: one per source disconnect, or one label indicating multiple disconnects must be opened. |
| AC disconnect, shock hazard, two sources 64-060(1)(h) · 84-024(1)(i) | All AC disconnects supplied from two sources of power, and every energy storage system disconnecting means (CEC 2024 Rule 64-914). |
| Ungrounded DC conductors 64-068(1)(b) · 64-066(7) | DC combiners, DC junction boxes, DC disconnects and inverters: ungrounded systems only. |
| Photovoltaic AC disconnect marking 64-074(1) | Each interconnecting AC power source: AC disconnects for inverters, panelboards, splitters. |
| Meter location and service box diagram 64-076(3) · 64-902(1) | At the meter location and service box. |
| Energy storage system warning 64-076(3) | At renewable-energy systems containing electrical energy storage. |
| Backfed breaker, do not relocate 64-112(4)(c) | At the PV input breaker in the electrical panelboard. |
| Photovoltaic DC disconnect marking 64-200(1) | String inverters: PV output circuit DC disconnect, at an accessible location. |
| Rapid shutdown at the DC disconnect 64-200(2) | At the disconnecting means for the photovoltaic output circuit. |
| Rapid shutdown placard at meter and service equipment 64-218(7) | At the supply authority meter location and the consumer's service equipment location. On buildings without exterior metering the location may need to be agreed with the local fire department. |
| Building source and disconnect location placard 64-076(3) · 64-902(1) (also shown by SK24 under 64-218(7) and 84-030(2)) | At the supply authority meter location and the consumer's service equipment. |
| Utility disconnect, do not lock 84-024(1)(i) | At the utility disconnect. |
| Interconnected system warning notice 84-030(1) | At the utility disconnect and the meter location. |
| Utility disconnect location callout 84-030 / MB TI 64-112 B (Manitoba) | At the meter socket, where the utility disconnect is permitted to be located other than adjacent. |
Rule numbers are printed as the source document writes them, and most provincial and utility standards were drafted against the 2021 Code. Nine Section 64 numbers changed in C22.1:24. The renumbering is here.
Manitoba kits
| Job | Plates here | Ontario |
|---|---|---|
| House, string inverter | 21 | 21 |
| House, microinverters | 17 | 17 |
| House with battery | 25 | 25 |
| Commercial rooftop | 30 | 30 |
| Ground mount / solar farm | 32 | 32 |
| Off-grid / cabin | 15 | 16 |
| Re-label an existing install | 8 | 8 |